The current status of the road construction projects is as follows;
- Resurfacing of South Jefferson Road from Ukraine Road to Eden Lane: The project was awarded on October 28, 2021, and contracts were received on December 3, 2021. A Pre-construction meeting was held Tuesday, July 12th. The Contractor anticipates the start of work in the 1st week of August.
- Resurfacing of Grand Avenue: The project was awarded May 12, 2022, and contracts were received June 9, 2022. The Pre-construction meeting was held on Tuesday, June 21, 2022. The contractor anticipates beginning work on July 25, 2022.
- Resurfacing of Ford Hill Road and Oak Place: The project was awarded May 12, 2022, and contracts were received May 26, 2022. The Pre-construction meeting was held on Monday, June 20, 2022. The contractor anticipates beginning work on July 25, 2022, and being substantially complete on August 12, 2022.
- Resurfacing of Polhemus Terrace, Behrens Drive, Andrew Road: The project was awarded May 12, 2022, and contracts were received May 23, 2022. The Pre-construction meeting was held on Monday, June 20, 2022. The Contractor began work on July 11th and anticipates being substantially complete on July 29th.
- Reconstruction of Manger Road: Field work completed June 9, 2022. The Project was advertised on July 12th with a bid reception scheduled for Tuesday, August 2nd. Anticipate a project award for the Township Committee meeting on August 11th.
- Resurfacing of South Jefferson Road from Eden Lane to Cedar Knolls Road: Plans and Specifications to be submitted to NJDOT for review on July 27, 2022