Morristown Airport's Runway 5-23 Rehabilitation Project Updates

" "

"DM AIRPORTS, LTD. is set to resume Phase II, Stage A Construction of the airport’s Runway 5-23 Rehabilitation Project in August 2020. The original project timeline was delayed due to COVID-19 impacts.

Morristown Airport’s Runway 5-23 is set for a major rehabilitation project over the next 7-10 years. Since 2005 DM AIRPORTS, Operators of Morristown Airport, has worked diligently with engineering firms, the Federal Aviation Administration, Airport Tenants, and other entities to minimize the operational impact for all those who fly with MMU while ultimately providing the best possible facility at project end. With a newly paved surface, upgraded approach systems, enhanced safety areas, lighting upgrades, and more, MMU will continue to shine as a premier general aviation airport for the New York Metro Airspace, State of New Jersey and Morris County.

An updated schedule for the upcoming phase of the Runway 5-23 Rehabilitation Project is now available. Please see below for a timeline and details for Phase II, Stage A.

All construction dates listed below are subject to change. DM AIRPORTS, LTD. will provide updated information if necessary. 

For more information on Phase II, Stage A of the Runway 5-23 Rehabilitation Project, please visit: MMUair.com/runway523


Runway 5-23 | Phase II, Stage A

August 10 - 17

  • Survey Work, Prep and Re-mobilization begins
    • No airfield impacts


RUNWAY IMPACTS

August 17 - 21: Runway 13-31 

  • Five (5) DAYTIME-Closures | 0700L - 1900L
  • Runway 5-23 REMAINS OPEN during these closures

August 23 - October 21: Runway 5-23

  • 60 NIGHTTIME-Closures | 2200L - 0600L
  • Runway 13-31 REMAINS OPEN during these closures"

For more information please visit MMU's website